This open house was active from April 7 - May 3, 2020. Information on this website may no longer be current. Email us for more information.
The project team evaluated four design alternatives for the Farmington and River roads intersection (including a traffic signal and three roundabout alternatives) using seven key criteria. The results of the alternatives analysis is below.
Evaluation Criteria |
Single lane roundabout alternatives |
Signalization |
|||
---|---|---|---|---|---|
Centered on intersection |
Off center |
Southwest |
Intersection |
||
Safety |
Intersection safety |
4 |
5 |
5 |
3 |
Roadway geometry |
Intersection design speed |
25 |
25 |
25 |
50 |
Traffic operations |
Operational performance intersection Opening day: 2022 Future demand: 2040 |
4 |
4 |
4 |
2 |
Construction impacts |
Driveways/Farms and other access points impacted |
12 |
11 |
9 |
13 |
Complexity of Construction and Schedule |
1 |
2 |
4 |
2 |
|
Costs |
Estimated Construction cost |
$$$ |
$$ |
$$ |
$ |
Right-of-Way impacts |
Right-of-way (acres) |
1.4 |
1.4 |
2.1 |
1.4 |
Structure Impacts |
2 |
2 |
2 |
2 |
|
Natural environment |
Floodplain Impacted |
No |
Yes |
Yes |
No |
Impervious Surface Area (ac) |
2.7 |
3.2 |
3.4 |
4.3 |
Notes:
- Transportation Research Board. 2010. NCHRP Report 672 Roundabouts: An Informational Guide, Second Edition.
- Growth is based on traffic volumes that were seasonally adjusted with a 'commuter' trend factor.
- Driveways / Farm and other access points currently within project limits.
- Ranking of costs includes assumptions of right‐of‐way acquisition, environmental mitigation, construction cost and scheduling.
- Estimated area of additional Right‐of‐Way and Temporary Easement needed for each alternative.
- Affected area includes construction in or around ditches and wetlands.
- Estimated area of total impervious surface with new construction.
- Operational performance based on the average queuing length and average vehicle delay.